A buyer asks a solar-plus-storage site for four more megawatts during the next hour. The battery is charged, and its inverter can deliver four megawatts. Can the scheduler accept? Give a candidate the diagram before giving them a spreadsheet. The buyer measures delivery where the site connects to the grid. Solar output and battery discharge share that connection.
Put the meter in the hiring exercise
Draw a fictional site with a 10 MW export limit. Solar is producing 9 MW, the site itself uses 1 MW, and the battery is idle. The grid meter reads 8 MW of net export. Label every quantity with its direction. Ask the candidate to draw the effect of a 4 MW discharge while the other readings hold. It would take net export to 12 MW. Only 2 MW of additional export fits. Cutting solar output could make room for more battery discharge, but it would not give the buyer the extra 4 MW at the meter.
The U.S. Energy Information Administration explains how battery duration relates energy capacity to power capacity. Use its distinction in the second stage of the exercise. Give the battery 3 MWh available for delivery on the AC side after reserve and losses. At a constant 2 MW, the additional hour needs 2 MWh. Now change the request to two hours: there is room at the connection under the original readings, but the battery would need 4 MWh. Ask the candidate to show which constraint is binding in each case.
Change the forecast after the desk says yes
Thirty minutes into the one-hour schedule, clouds reduce solar output to 5 MW. Site demand holds at 1 MW. The customer expected a total of 10 MW, and the meter would now read only 6 MW with the battery still discharging at 2 MW. Even at its 4 MW inverter limit, the battery can bring export only to 8 MW. A useful display tells the operator how much of the commitment is at risk and for which interval. A green icon beside the battery tells the buyer very little.
Give every applicant the same readings, timestamps and rounding rules. Ask for a short schedule showing solar production, site use, battery output, available energy and net export. Then hide the newest meter reading. Score whether the applicant marks the estimate, shows the age of the last observation and refers a changed commitment to the person authorized to make it. Accept a spreadsheet, a diagram or a short program if a second operator can reproduce the decision.
Decide who can promise the next megawatt
The site engineer owns the diagram, the operating limits and the measurement boundary. The scheduler owns the proposed delivery against a stated baseline. The operator owns the reading and the handoff when a limit changes. Before using the display for an actual commitment, have a second shift replay both intervals from the supplied figures. It should find the same shortfall, identify the first affected interval and know whom to notify while the buyer can still act.